Topic:       *Glencoe Stormwater Tunnel*



Speakers: Ian Morley, P.Eng., City of Calgary

                Henry Crawford, P.Eng., M.E.Sc <http://m.e.sc/>., Thurber
Engineering Ltd.

Place:       Blackfoot Inn, 5940 Blackfoot Trail SE, Calgary

Time:        5:30 pm – Cocktails and Registration

                6:30 pm – Dinner

                7:15 pm – Presentation

Cost:        Students: $10

                CSCE / CGS Members: $ 25

                Non-Members: $ 35

Sponsor:*   *Thurber Engineering Ltd.

**

*Please register your attendance with APEGGA at (403) 262-7714 at least one
 day prior to event.*



Abstract:

The City of Calgary Water Resources engaged the City of Edmonton Drainage
 Services to construct a 935 m long tunnel below 27 Avenue SW to provide
 temporary storage of stormwater and reduce the risk of flooding in the
 community of South Calgary.



The tunnel is 935 meters in length with an internal diameter of 2940 mm and
 varies in depth from 20 meters at the east end (15 Street) to 42 meters at
 the west end (20 Street).  Construction was started on the tunnel entry
 shaft in April of 2005 and the TBM (tunnel boring machine) was installed in
 early August of 2005.  Construction of the tunnel portion of the project was
 complete by June of 2006.



The presentation will describe why a deep tunnel was chosen as the preferred
 method of controlling stormwater at this location.  It will also describe
 the probabilistic method used to predict the long term stresses on the
 permanent tunnel liner and compare the predicted stresses with the results
 of on-going monitoring.



About the Speakers:

Ian Morley is the Team Leader for The City of Calgary, Water Resources,
 Infrastructure Delivery, Project Engineering – Underground Team.  The
 Project Engineering Team is responsible for the management and delivery of
 City capital projects for the sanitary sewer collection system, the drainage
 conveyance system and the water distribution system.



Henry Crawford is a senior geotechnical engineer and principal with Thurber
 Engineering Ltd. in Calgary.  Henry has been actively involved with numerous
 City of Calgary infrastructure projects, including projects for Calgary
 Roads, the Transportation Infrastructure Office, Solid Waste Services and
 Water Resources.



------------------------------

Distributed on behalf of the CSCE Calgary Section.

Please let us know if you wish to be removed from the CSCE email
distribution list.


 Rainer Herzinger
CSCE Calgary Section Chair
www.cscecalgary.ca



More information about the engg-enci-L mailing list